Scope : Construction of Bhanupali-Bilaspur-Beri new railway line in the district Bilaspur of Himachal Pradesh (Package-5).
Dilip Buildcon has been declared as the lowest (L1) bidder for the tender floated by the Rail Vikas Nigam (RVNL) for railway project on percentage rate (EPC project) in the state of Himachal Pradesh.
The project is for construction of tunnels T14, T15 and T16, bridges and formation works from ch 40.430 to 44.925, including slope protection works and allied works in connection with Bhanupali-Bilaspur-Beri new railway line in the district Bilaspur of Himachal Pradesh (Package-5). The bid project cost is Rs 636.98 crore and completion period is 24 months.
On April 2023, H G Infra Engineering has received a letter of acceptance (LoA) dated 4 April, 2023 from Rail Vikas Nigam (RVNL) for a work order in connection with the Bhanupali-Bilaspur-Beri railway line in Himachal Pradesh. RVNL's estimated project cost was Rs 535.15 crore, and the bid quoted by HG Infra was Rs 466.11 crore, making it the lowest bidder (L-1).
The construction work includes foundations, substructure and superstructure along with river training/protection work, earthwork and allied works for viaduct-I and II between ch km 47+415 to km 50+9000, for a total length of 3.485 km.
The contract, which has a completion period of 30 months, is mandated to commence within 42 days from the date of receipt of LoA.
On February 2023, H G Infra Engineering has been declared as L-1 bidder by Rail Vikas Nigam (RVNL) for the Bhanupali-Bilaspur-Beri new railway line project in Bilaspur district of Himachal Pradesh.
The scope of work includes, the construction of foundations, substructure and superstructure along with river training/protection work, earthwork & allied works for viaduct 1 & 2 in between chainage km 47+415 to km 50+900, in connection with Bhanupali-Bilaspur-Beri new railway line. The total length covered is 3.485 km under the project.