π Tender Overview
Scope of Work:
Construction of East Sitra Housing Project - Third Phase.
Description:
CMEC will construct 1,269 new housing units as well as secondary infrastructure. Work is set to commence in Q1 2025 and is expected to cost $315.7 million (BD119 million). The Sitra projectβs third phase spans 670,000 square metres and features 23.6 kilometres of main and secondary road network as well as a 22.8km sewage network, 27.6km rainwater drainage network, and an integrated lighting system with 753 lampposts. The third phase also includes 36 power substations and six telecom towers, as well as amenities like a shopping mall, five commercial centres, three schools, a cultural centre, auditorium, and a child development centre. Additionally, the project includes an afforestation plan with a central park, six gardens, childrenβs play areas, and 52.3km of green spaces with 1,644 trees.