π Tender Overview
Scope of Work:
To Build Fifth natural gas liquids (NGL) train at NGL complex in Qatarβs Mesaieed Industrial City.
Description:
The objective of the project is to build a fifth NGL train (NGL-5) with the capacity to process up to 350 million cubic feet a day of rich associated gas from QatarEnergyβs offshore and onshore oil fields. The following contractors are understood to have expressed interest in participating in the projectβs main contract tendering process: ?CTCI Corporation (Taiwan), Larsen and Toubro Energy Hydrocarbon (India), McDermott (US), Saipem (Italy), Samsung E&A (South Korea), ?Tecnicas, Reunidas (Spain), Tecnimont (Italy).
QatarEnergy began site preparation for the project in the fourth quarter of 2023 and expects work to complete in the first quarter of 2025. QatarEnergy intends to start operations at the NGL-5 facility by the second quarter of 2028.
Associated gas from the PS1, PS2 and PS3 offshore fields and the Dukhan onshore field gets processed at existing facilities in the NGL complex at Mesaieed β the FSP, NGL-1 and Qapco ERU units. The planned NGL-5 facility will replace the three units at the Mesaieed complex and process gas from the PS1, PS2 and Dukhan fields.
The scope of work on the project involves EPC of units for the following functions: Feed gas compression, Slug handling, Gas sweetening, Dehydration, Mercury removal, NGL fractionation, NGL recovery, Product treatment, Propane refrigeration, Acid gas enrichment, Sulphur recovery, Anti-flaring, Utilities, Boil-off gas recovery, Drains and collection networks, Effluent water treatment plant, Carbon dioxide treatment and sequestration/export, Brownfield modifications, Product rundown pipelines. QatarEnergy plans to divide the scope of work on the NGL-5 project into five EPC packages.
Previous events:
June 2024- QatarEnergy issued the expression of interest (EoI) document for the NGL-5 project. Due date was - 24 June 2024.