Scope: IATI identify:P-46002-Z1-FA0-152
Country Multinational
Approval Date Dec 15, 2017
Signature Date 07 Mar 2018
Planned Completion Date 31 Dec 2022
Last Disbursement Planned Date 31 Dec 2022
Sector Power
DAC Sector Code 23010
Commitment:UA 27,500,000
Status Implementation
Funding Fragile States Facility
Implementing National Electricity Company (SNE)
Finance Type:Aid Grant Excluding Debt Reorganization
Flow Type:ODA
Aid Type:Project Type Interventions
Commitments UA 27,500,000
Fragile States Facility UA 27,500,000
Context:The Cameroon-Chad interconnection line is recognized in the energy exchange scheme between the member states of the Economic Community of Central African States (ECCAS), as one of the important infrastructures to be built for the exchange of energy. of energy within this space. The Cameroon-Chad Interconnection Project, as envisaged today, includes on the one hand the Ngaoundere-Maroua (Cameroon) - N'Djamena (Chad) section of approximately 700 km, and a Maroua (Cameroon) -MogromNdjamena ( Chad) of about 250 km as far as the interconnection itself is concerned, and on the other hand the rural electrification component along the corridors of the transmission lines. The study, with a cost excluding taxes estimated at UA 3.060 million, will be carried out over a period of 20 months from January 2014.
Project Objectives The sectoral objective of the study is to strengthen regional cooperation and integration, and improve access to electricity. The specific objectives of the study are: (i) to examine the technical, economic and financial feasibility, as well as the environmental and social impact of the interconnection project, (ii) to study the electrification of the localities located along the transmission lines, (iii) define the institutional and commercial framework of the project, (iv) prepare draft Memoranda of Understanding for the defined institutional and commercial frameworks, as well as the tender documents .*****Projects Title Change
More Details Added
End Date 31 Dec 2022
Project Phase Execution