π Tender Overview
Scope :
The Kapar Combined Cycle Power Plant is 2,100MW gas fired power project. It is planned in Selangor, Malaysia. The Kapar Combined Cycle Power Plant is 2,100MW gas fired power project. It is planned in Selangor, Malaysia.
Description
The project is being developed and currently owned by TNB Power Generation Sdn and Widad Business Group Sdn. The company's ownership stake in the project stands as 60% and 40% respectively.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
The project cost is expected to be around $2,008.215m.
Development status
The project construction is expected to commence from 2030. Subsequent to that it will enter into commercial operation by 2031.
Description
The project is being developed and currently owned by TNB Power Generation Sdn and Widad Business Group Sdn. The company's ownership stake in the project stands as 60% and 40% respectively.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
The project cost is expected to be around $2,008.215m.
Development status
The project construction is expected to commence from 2030. Subsequent to that it will enter into commercial operation by 2031.