๐ Tender Overview
Project Location Meghalaya, India
Project Developer North Eastern Electric Power
Mawphu II is an 85MW hydro power project. It is planned on Umiew river/basin in Meghalaya, India.It will be developed in a single phase. The project construction is likely to commence in 2025 and is expected to enter into commercial operation in 2027.
Description
The project is being developed and currently owned by North Eastern Electric Power.
Mawphu II is a run-of-river project. The hydro reservoir capacity is planned to be 1.7 million cubic meter. The gross head and net head of the project will be 320m and 230.5m respectively. The project is expected to generate 331.09 GWh of electricity.
The hydro power project consists of 2 turbines, each with 42.5MW nameplate capacity.
The nameplate capacity of electric generator(s) to be installed at the project site is 47.3 MVA.
Development status
The project construction is expected to commence from 2025. Subsequent to that it will enter into commercial operation by 2027.