Location: Sokhna integrated zone.
Investment: โฌ3.9 billion.
Scope of Work:
To Develop 900,000 tonnes/year Green ammonia project - Phase 1 in Sokhna integrated zone.
Pilot Phase: Annual production capacity of 100,000 tonnes, commercial operations by Q4 2029.
Phase 1: Production capacity of 900,000 tonnes/year, commercial operations by Q4 2031.
Background:
The agreement was signed by Chairman of SCZONE, CEO of the New and Renewable Energy Authority (NREA), and CEO of The Sovereign Fund of Egypt (TSFE).
Other Owners:
1) New and Renewable Energy Authority (NREA)
Dr.Ibrahim Abo Elnga St. Ex. of Abbas El-Akkad St. - Nasr City - Cairo, Egypt
Tel: +20 2 22710081
http://nrea.gov.eg/
2) Sovereign Fund of Egypt (TSFE)
3 Abul Feda Street, 12th Floor, Zamalek, Cairo, Egypt 11211
https://tsfe.com/